Problem is the Convo , specifically the back of the Convo is in the 100 year flood stage and building there is prohibitive a practice facility adjacent to the Convo would be very difficult to swing. The new flood plains were drafted several years ago.
This was discussed on another thread a while back.
Building in a 100 year flood zone is really tough.
I don't know if Ohio has regulations that are more restrictive then FEMA's,New Jersey does,but just following FEMA's are tough.
You'd have to build the building a minimum of 1 foot above the 100 year flood
elevation.
Depending on restrictions on placement of fill in a Flood Plain,you'd either have to build the building on stilts,or compensate for the fill volume by creating what's called a "net fill compensation area" of equal volume to the fill.
Then,because you're increasing impervious coverage,you'd need an extensive
drainage system to assure no impact downstream of the project site.
And just to throw a bit more cold water on the location.
Based on soil conditions,you have to put any building on piles.